4 machine set-up and operation, Floor brake operation, 4 machine set-up and operation -5 – JLG 15AMI Operator Manual User Manual
Page 43: Floor brake operation -5, Setting & releasing floor brake -5

SECTION 4 - MACHINE OPERATION
3121212
– JLG Lift –
4-5
4.4 MACHINE SET-UP AND OPERATION
The following sequence of set-up procedures must be followed
to safely operate this machine.
1. Position machine in work area. Work area must be a
smooth, firm, level surface.
NOTE: If AC powered machine, connect machine to a grounded
AC receptacle with a heavy duty extension cord equipped
with an equipment grounding conductor. Also, the cord
must be capable of handling the maximum amperage draw
of the machine’s electric pump motor.
If DC powered machine, be sure battery box assembly is
installed, battery is charged and connected to the
machine’s DC input receptacle.
2. Set power on/off key switch to the ON position at the
ground control station.
3. Check both emergency stop switches, one on platform
control station and one on ground control station that they
are in the reset position for operation.
4. Check if manual descent control valve is closed.
5. Set floor brake, see steps following.
Floor Brake Operation
1. At the front of the machine under the base frame, engage
and lock the floor brake down into position
Figure 4-4. Setting & Releasing Floor Brake.
1. To Set Floor Brake - Push
Down till Pedal Locks in Place.
2. To Release Floor Brake - Push
Down on Release Rod