2.5 Vent piping

1. Install 5" to 4" reducer pipe on top of the water

heater and then connect a 4" 90º elbow to begin

the horizontal run. Use 4” vent pipe to connect

from this elbow to the power vent motor inlet,

avoiding elbows when possible. The maximum

vent length from the water heater to the point of

termination is 25 feet with one elbow. (Fig. 5) If

using more than one 90° elbow, subtract 5 feet

off the maximum vent length for each additional

elbow used. A maximum of three elbows is

allowed. The minimum straight vent length is 2

ft.

2. Support the vent pipe in accordance with vent

pipe manufacturer’s instructions. Vent pipe is not

supplied in the power vent kit, with the exception

of the 5" to 4" reducer in the AQ4 kit. Observe

the clearances associated with the class of vent

pipe used. 4" single wall galvanized, 4" stainless

steel or 4" B-vent pipe is required.

2.6 Linear safety spillage switch

The linear safety spillage switch provides a means for

safety shut down of the water heater in the event of

flue blockage or power vent failure. If hot flue gases

spill from the draft hood diverter, the draft spillage

sensing switch will open the pilot safety circuit and

shut off all gas to the water heater. The switch is

normally closed and opens at temperatures greater

than 185º F. It has a manual reset button.
Mounting the linear safety spillage switch
1. Attach the spillage switch to the top left of the

heater’s draft diverter using the existing hole and

the included mounting screw. (Fig. 6)

2. Lay copper capillary sensing tube across top of

the draft diverter. Allow excess tube to hang down

right side of heater. Do not cut or crimp capillary

tube.

3. Route the two wires from the spillage switch

down the left side of heater to the ECO keeping

the cables out of contact with hot surfaces. (Fig.

6)

Connecting linear safety spillage switch to pilot

safety circuit
The ECO/temperature limiter is mounted on the

lower left outlet water pipe. (Fig. 7)

1. Remove one wire lead connected to ECO terminal

(it does not matter which one is disconnected).

2. Attach ¼" quick connect terminal end of linear

spill switch cable to now exposed terminal of the

ECO.

3. Connect the male spade connector to the removed

lead wire from step 1. See the wiring diagram in

Fig. 13 to confirm proper set up.

Fig. 5 Venting setup

AQ4 Installation instructions

Fig. 6 Linear safety spillage switch mounting

Fig. 7 ECO location

ECO terminals

This manual is related to the following products: