8 Operation

The switch may only be put into service and operated by authorized persons. Do not use any hard
objects for making entries. A self-test is performed on first commissioning.

The pressure switch is operated via two membrane keys. These must not be touched by means of
hard objects.

IMPORTANT

When power supply is switched on the operational status of the switch is indicated by a green
LED. The switching function is not optically indicated.

9 Programming

IMPORTANT

The pressure switch is programmed by means of the membrane key

s

(T1) and

(T2).

9.1 Version with one switch point

*

The switch point SP is set to the measuring range end value.

**

The re-actuation point RS is set to the measuring range end value.

Function

Membrane keys

LED

Activate teaching

Press the membrane keys

(T1) and

(T2) for 4 s.

The LED flashes alternatingly for 12 s red
and green. Subsequently the LED shines
green.

SP teaching

Press the membrane key T1 for 4 s.
The current value for the SP is
transferred to the pressure switch.

NOTE

When the operation is aborted, the SP
is not updated.

The LED shines red for 4 s.
The LED flashes red 3x, after the pressure
switch has updated the SP.

Subsequently the LED shines green.

RS teaching

Press the membrane key T2 for 4 s.
The current value for the RS is
transferred to the pressure switch.

NOTE

When the operation is aborted, the RS
is not updated.

The LED shines green for 4 s.
The LED flashes green 3x, after the
pressure switch has updated the RS.

Subsequently the LED shines green.

Activate/actuate
Reset SPError!
Reference source not
found.

Switch the pressure switch on while
pressing the membrane key T1.
Press the membrane keys T1 and T2
for 4 s.

The LED flashes for 12 s red and green at
the ratio of 1:3. Subsequently the LED
shines green.

3 Standards

The standards applied during development, manufacture and configuration are listed in the CE
conformity and manufacturer's declaration.

4 Warranty/Guaranty

Warranty

Our scope of delivery and services is governed by the legal warranties and warranty periods.

Terms of guaranty

We guaranty for function and material of the pressure switch under normal operating and
maintenance conditions in accordance with the statutory provisions.

Loss of guaranty

The agreed guaranty period will expire in case of:
• incorrect

use

• incorrect installation or

• incorrect handling or operation contrary to the provisions of these operating instructions
No liability is assumed for any damage resulting therefrom, or any consequential damage.

5 Installation/Commissioning

DANGER

Only install or uninstall the switch when deenergized (electrically and
hydraulically/pneumatically).

Pressure connection and electrical connection must be carried out by trained or instructed
personnel according to state-of-the-art standards.

The switch must only be installed in systems where the maximum pressure P

max

is not exceeded

(see type label).

WARNING

Be aware of the fact that in case of operation with higher temperatures the casing surface may
become very hot!

CAUTION

Mount the pressure switch from the bottom to the fitting with a wrench SW 24 and tighten to a
torque of 45 Nm torque.

Do not put the switch into operation when the switch itself or the connection cable is damaged.

Avoid impact and severe vibration during transport. Even if the switch housing remains
undamaged inside parts may be damaged and cause malfunctions.