5. Install the purlins with (4)
3
/
8
” x 5.5” bolts,
(4) washers, (4) lock washers, and (4) nuts
each. Fully tighten all purlins.
6. For shelters with Dero Decker racks, install the DD
beams with (8) 5/8” x 2” carriage bolts, (8) lock
washers, and (8) nuts each. Leave finger-tight.
Carriage bolts at the end of the shelter should have
the heads facing out. See shelter assembly drawing
for specific DD beam placement locations.
7. For shelters with side panels, install the front and
side panel supports between every upright,
except where the door will be installed. Align
slots in the panel support with the slots in
the upright, drill 3/8” diameter holes, and fasten
with 3/8” wedge anchors with nuts finger-tight.
8. For polycarbonate panels, install the panels with (4)
8mm bolts and (4) lock washers. (2) 130mm bolts on
top and (2) 65mm bolts on the bottom. The bolts will be
received by square nuts that slide into the panel
grooves. The gap on top of the panel will be filled with
(2) 1.25” aluminum spacers and several washers if
needed. The uprights and panel supports may be
slightly moved in order to get the panels as square as
possible.
For wire mesh panels, install the panels with (4) 5/16”
bolts and (4) lock washers. (2) 5.5” bolts on top and (2)
3” bolts on the bottom. The bolts will be received by
rivet nuts in the panels. The gap on top of the panel will
be filled with (2) 1.25” aluminum spacers and several
washers if needed.
9. Once all the panels are properly placed,
tighten all the upright anchors and bolts
attaching the trusses. The carriage bolts
attaching the DD beams can also be tightened.