Preparing the System
Filling the System
At the beginning of each day or shift, fill the sinks with water that is
metered to approximately the correct operating temperatures:
• Wash sink (115°F / 48°C)
• Rinse sink (75°F / 24°C)
• Sanitizer sink (75°F / 24°C)
All sinks should be filled to, but not above, the “waterline” marks.
Fill the wash sink (the sink with the water jets) with water that is
approximately 115°F / 48°C. Use the hot and cold taps on the faucet to
adjust the water to the appropriate temperature. A good rule of thumb is
that the water should be hot to the touch but not so hot that it is
uncomfortable.
Rinse Water
If the preferred method for rinsing wares is of the “submersion” type, fill the
rinse sink (middle sink) with water that is approximately room temperature,
75°F/24°C. There is no need to fill the rinse sink if the preferred method is
to use the sprayer for rinsing wares.
Sanitizer Water
Fill the sanitizer sink (the last sink) with water that is approximately room
temperature, 75°F / 24°C.
A Chemical Company Should Be Aware of the
Following:
The detergent must be low foaming, metal/aluminum-safe and not
excessively caustic. Most standard sanitizers are acceptable.