4.4 Technical data - remarks

for
- Principal dimensions
- Pressure-temperature-ratings, etc. refer to datasheet.

4.5 Marking

Details of the CE-marking on the valve:

5.0 Installation

5.1 General notes on installation

The following points should be taken into account besides the general principles governing
installation work:

CE-marking

0525 Notified body

Manufacturer

Address of manufacturer:
refer to item 11.0 Warranty / Guarantee

Typ

Type

Bj.

Year of manufacture

According to the Pressure Equipment Directive table 6, annex II, valves without safety
function are only allowed to bear the CE-marking DN32 onwards.

ATTENTION !
- Remove flange covers if present.
- The interior of valve and pipeline must be free from foreign particles.
- Note installation position with reference to flow, see mark on valve.
- Steam line systems should be designed to prevent water accumulation.
- Lay pipelines so that damaging transverse, bending and torsional forces are

avoided.

- Protect valves from dirt during construction work.
- Connection flanges must mate exactly.
- Connecting bolts for pipe flanges should be mounted preferably from the

counter flange side (hexagon nuts from the valve side).
At DN15-32: If valves should be mounted directly to valves, the upper flange
connecting bolts should be preferably executed with studs and hexagon nuts on
both sides.

- Valve mountings such as actuators, handwheels, hoods must not be used to

take external forces, e.g. they are not designed for use as climbing aids, or as
connecting points for lifting gear.

- Suitable materials handling and lifting equipment should be used.

See data sheet for weights.

- Valves can be installed with the spindle pointing in any direction, but the

prefered spindle position is vertical.

- Valves should be installed upside down only, if the medium being handled is

clean.