OPERATION

60C 01/10

Operation Section 4-5

© 2010 Alamo Group Inc.

OPERA

T

ION

© 2010 Alamo Group Inc.

Position the unit so the backhoe swing post is over

the center line of the trench connection. Dig with the

backhoe at extreme swing positions, and in as close

to the stabilizers as possible. Pile the soil on the

opposite side of the trenches.

Position the unit forward with the lift and crowd levers so
the two trenches can be connected. Pile the spoil on the
opposite side of the trench.

SIDE SLOPE EXCAVATING OR TRENCHING

Dig with the backhoe uphill whenever possible.

Level the backhoe on slopes with the stabilizers to dig

plumb trenches, or use the backhoe or loader to cut a level

slot for the uphill wheel and stabilizer. Pile the slot on the

low side.

When on the side of a steep slope, cut a level surface

along the uphill side of the trench with the loader.
Pile the spoil of the cut downhill. When digging, pile the

spoil of the trench uphill.

Dig field trenches progressively. As soon as one trench is

completed, have the work men lay the tile. Start the next

trench, using the spoil to fill the previous trench.