5 operation, 1 pre-startup checklist, 2 operating sequence – Sterlco SPL Series Powder Hopper Loader User Manual
Page 27
![background image](/manuals/373384/27/background.png)
Powder Hopper Loaders
Page 27
5 Operation
5-1 Pre-Startup
Checklist
; Are all electrical connections correct, secure, and to code?
; Is the compressed air connection secure and safe?
; Is the receiver level and mounted securely?
; Are the flex hose and pick-up wand secure?
; Is the flexible hose properly grounded?
; Can the material level switch activate without obstruction?
; Can the material discharge valve swing without
obstruction?
5-2 Operating
Sequence
1. Blowback
sequence.
2. Motor
starts.
3. Flapper discharge valve seals under vacuum.
4. Material
conveys.
5. Vacuum receiver fills.
6. Vacuum timer times out.
7. Motor
stops.
8. Blowback sequence begins, the flapper discharge valve
opens under the weight, and material dumps.
Steps 1 through 8 repeat automatically.
If the level switch remains open, the receiver loader remains idle
until the material level in the bin drops and frees the
counterbalanced dump valve. Steps 1 through 8 in the loading
sequence as listed above then resume automatically.