beautypg.com

Vent pipe system, Draft hood installation, Vent pipe size – American Water Heater 318935-003 User Manual

Page 10: Vent connectors

background image

10

Vent Pipe System

This water heater uses a non-direct, single-pipe vent system

to remove exhaust gases created by the burning of fossil fuels.

Air for combustion is taken from the immediate water heater

location or is ducted in from the outside (see “Combustion Air

Supply and Ventilation” section).
This water heater must be properly vented for the removal of

exhaust gases to the outside atmosphere. Correct installation

of the vent pipe system is mandatory for the proper and

efficient operation of this water heater and is an important

factor in the life of the unit.
The vent pipe must be installed according to all local and state

codes or, in the absence of local and state codes, the “National

Fuel Gas Code”, ANSI Z223.1(NFPA 54)-current edition. The

vent pipe installation must not be obstructed so as to prevent

the removal of exhaust gases to the outside atmosphere.
IMPORTANT: The use of vent dampers is not recommended

by the manufacturer of this water heater. Although some vent

dampers are certified by CSA International, this certification

applies to the vent damper device only and does not mean

they are certified for use on this water heater.
U.L. recognized fuel gas and carbon monoxide (CO) detectors

are recommended in all applications and should be installed

using the manufacturer’s instructions and local codes, rules, or

regulations.
IMPORTANT: If you lack the necessary skills required to

properly install this venting system, you should not proceed,
but get help from a qualified person.

Draft Hood Installation

Align the legs of the draft hood with the slots provided.

Insert the legs and secure the draft hood to the water

heater’s top with the four screws provided as shown in

Figure 9. Do not alter the draft hood in any way. If you are

replacing an existing water heater, be sure to use the new

draft hood supplied with the water heater. IMPORTANT:

50K models must use the supplied 4” draft hood. See
Figure 9.

Vent Pipe Size

It is important that you follow the guidelines in these

instructions for sizing a vent pipe system. If a transition to

a larger vent size is required, the vent transition connection
must be made at the draft hood outlet.

Vent Connectors

1. Type B, Double wall, U.L. Listed Vent Pipe.
2. Single wall Vent Pipe.
Maintain the manufacturer’s specified minimum clearance from

combustible materials when using type B double wall vent

pipe.
Vent connectors made of type B, double wall vent pipe

material may pass through walls or partitions constructed

of combustible material if the minimum listed clearance is

maintained.
Maintain a six inch minimum clearance from all combustible

materials when using single wall vent pipe.
IMPORTANT: Single wall vent pipe cannot be used for water

heaters located in attics and may not pass through attic

spaces, crawl spaces or any confined or inaccessible location.

A single wall metal vent connector cannot pass through any

interior wall.
When installing a vent connector, please note the following:

Install the vent connector avoiding unnecessary bends,

which create resistance to the flow of vent gases.

Install without dips or sags with an upward slope of at least

1/4-inch per foot.

Joints must be fastened by sheet metal screws or other

approved means. It must be supported to maintain

clearances and prevent separation of joints and damage.

The length of the vent connector cannot exceed 75% of

the vertical vent height.

The vent connector must be accessible for cleaning,

inspection, and replacement.

Vent connectors cannot pass through any ceiling, floor,

firewall, or fire partition.

It is recommended (but not mandatory) that a minimum 12

inches of vertical vent pipe be installed on the draft hood

prior to any elbow in the vent system to improve conditions

for positive flow of venting gases.

IMPORTANT: Existing vent systems must be inspected for

obstructions, corrosion, and proper installation.

Figure 9

Draft hood Inst allation

Sheet Metal Screws (four provided)

Draft hood

Jacket top

Install the draft hood with

the four screws provided.

Slot

Slot

Legs

Legs

Sheet Metal Screws (four provided)

Draft hood

Jacket top

Install the draft hood with

the four screws provided.

Slot

Slot

Legs

Legs

4” Draft Hood
(50K Models)

3”- 4” Draft Hood
Combination

Alternative
Opening
Location

1 sq. Inch

Per 3000 BTU/HR

Confined
Space

Figure 8B
All Air from Outdoors
Using a Single Permanent Opening