Installing the FC16-64
Before you begin
Be sure to establish a naming or numbering scheme before you begin attaching cables. Each cable
should have a unique designation and should be labeled accordingly. You should also record this
information separately for future reference and troubleshooting. If you are using break-out cables,
remember to label appropriately that you know which ends are being connected. Refer to the serial
numbers on the break-out side of the cables for proper identification of individual channels or ports.
ESD precautions
The Brocade DCX Backbone series contains ESD-sensitive field-replaceable units (FRUs). When
working with any FRU, use correct electrostatic discharge (ESD) procedures.
•
Wear a wrist grounding strap connected to chassis ground or a bench ground.
•
Store ESD-sensitive components in antistatic packaging.
Time required for installation tasks
•
Installing a single FC16-64 in a chassis should take less than five minutes.
•
Refer to the documentation accompanying any patch panels for the approximate time to install and
pre-cable the panels.
•
Attaching cables, bundling and routing them, and attaching the cables to the patch panel for one
FC16-64 should take approximately 40 minutes, depending on experience and the ability to work
with cable connections.
Items required
You should have the following items before you start installing FC16-64 port blade: