beautypg.com

Installation - concrete application – King Electric TCM User Manual

Page 9

background image

STEP 9: RECORD INFORMATION AND AFFIX LABELS

• Ensure that all resistances measured for Before, During, After and Final Commissioning are recorded in the TC Cable / TCM Mat Testing
Log
.

• The six digit product code found on the TC cable/mat power lead must be recorded in the TC Cable / TCM Mat Testing Log.

• Install the electrical panel label at the electrical panel, indicating the location of the cable.

• Install the Warning label in a visible area of the floor, for the duration of the construction.

It is also recommended that the label be kept in a suitable location on a permanent basis.

SAVE THESE INSTRUCTIONS

INSTALLATION - CONCRETE APPLICATION

APPENDIX A: TYPICAL TC/TCM WIRING DIAGRAM

This manual is related to the following products: