STEP 9: RECORD INFORMATION AND AFFIX LABELS
• Ensure that all resistances measured for Before, During, After and Final Commissioning are recorded in the TC Cable / TCM Mat Testing
Log.
• The six digit product code found on the TC cable/mat power lead must be recorded in the TC Cable / TCM Mat Testing Log.
• Install the electrical panel label at the electrical panel, indicating the location of the cable.
• Install the Warning label in a visible area of the floor, for the duration of the construction.
It is also recommended that the label be kept in a suitable location on a permanent basis.
SAVE THESE INSTRUCTIONS
INSTALLATION - CONCRETE APPLICATION
APPENDIX A: TYPICAL TC/TCM WIRING DIAGRAM