The following table contains the screw
tightening torque values, to be set by
means of a torque wrench only:
12. SCREW CALIBRATION
13. MAINTENANCE TOOLS
Standard tools are required for the pump
maintenance but to facilitate the mounting
and dismounting operations of some pump
components, you will find the drawings to
make some tools on page 21.
14. PUMP STOPPED FOR LONG TIME
Before starting the pump for the very first
time after a long period from the date of
shipment check for the correct oil level,
check the valves as indicated in chapter
11 and then comply with the starting
procedures indicated in chapter 10. When
a long inactivity is scheduled drain the
entire suction and delivery line and then
run the pump dry only for a few seconds
in order to drain out the water collected
inside the fluid end.
15. PRECAUTIONS AGAINST FREEZING
In the risk of freezing the following
precautions should be taken:
-
after use drain the entire suction and delivery lines
(filter included) by means of discharging devices,
provided and positioned specifically for this purpose
along the lowest point of the lines.
-
run the pump only for a few seconds in order to
drain the water collected inside the fluid end.
Or when applicable
-
add a recommended amount of anti-freeze into the
water tank and run the pump until the anti-freeze
works all through the system.
If a pump is frozen or appears frozen ON NO ACCOUNT
SHOULD THE PUMP BE OPERATED until the entire
system has been thawed out.
DESCRIPTION
Ft. Lbs.
N-m
Kgm.
Valve cover
screws
7.3
10
1
Plunger Bolts
14.7
20
2
Connecting Rod
Screws
28
38*
4
Valve Plate
Screws
59
80**
8
Fluid End Bolts
29.5
40***
4
Suction Plug
73.7
100
10
Delivery Plug
88
120
12.2
Auxiliary Plug
29.5
40
4
*
The conrod screws must be tightened as
indicated in point D, page 13.
** The valve plate must be tightened following
the sequence indicated in fig. 28.
*** The fluid end screws must be tightened in 2
stages following the sequence indicated in
fig 24:
First stage: 20 N-m
Second Stage: 80 N-m