4-5

Flue Gas Analysis System

Operation 4

TELEDYNE BROWN ENGINEERING

Analytical Instruments

4.1.6

Routine Operational Calibration

Span calibration should be checked every two to four weeks on a

routine basis. Whenever there is the slightest suspicion of abnormal perfor-
mance, an inspection of the possible trouble should be made, followed by
span calibration. Use trouble shooting procedures as required.

4.2

Startup of Combustibles Analyzer

4.2.1

Procedure

The combustibles monitor comes ready to operate. Power is con-

nected to it through a terminal strip in the oxygen analyzer (see Figure 6).
The combustibles monitor has Its own POWER switch located on the front
panel of the control unit. Alarm relay and analog output terminals are
located in the oxygen analyzer.

When ready to operate, follow the startup procedure in Section 4.3

Startup Procedures, except as follows:

(1) Turn on the air supply and adjust the AIR regulating valve on

the valve panel until I flow rate of 2–3 SCFH is indicated on the
lefthand flowmeter.

(2) Open the SAMPLE toggle valve and open the sample/bypass

control valve fully CCW. The sample/bypass control valve is
the valve on the outlet of the filter.

(3) Start up the svstem pump and with either calibration air or

sample flowing, slowly close the sample/bypass valve until a
flow of 2–3 SCFH (matching air flow) is indicated on the
righthand flowmeter. The flowmeter ball will have some
bounce due to water column fluctuation in the system. Adjust
for an average value.

Note:

Do not attempt to run a higher flow rate than 3 SCFH. Higher flow
rates will cause the water
trap to break and all flow will be lost
through the drain.

(4) Turn ON the POWER switch of the combustible monitor

control unit. Wait about five minutes for the unit to warm up.

(5) Shut off the SAMPLE toggle valve and let only air flow

through the unit.