INSTALLATION AND MAINTENANCE.

• CHECK THAT THE SITE VOLTAGE AND POWER SUPPLY CORRESPOND TO THAT OF THE PUMP.
• CHECK THAT THE FUSES ARE INTACT.
• USE SHORTEST POSSIBLE HOSE OF THE CORRECT SIZE. AVOID CREASES, SHARP BENDS,

AND CONTRACTIONS.

• NEVER LIFT OR PULL THE PUMP BY THE CABLE. USE THE LIFTING HANDLE ON THE

PUMP. YOU MAY SUSPEND THE PUMP BY MEANS OF A ROPE OR PLACE IT ON A SOLID
BASE.

THE MAXIMUM PUMP SUBMERGENCE RECOMMENDED IS 60 FEET/20m.
THE SPECIFIC GRAVITY OF THE PUMPED FLUID SHOULD NOT EXCEED 1.1.
• CHECK THE INSULATION RESISTANCE OF THE WINDING WITH RESPECT TO THE BODY. IT

MUST BE MINIMUM 5 MEG-OHMS.

• CONNECT THE PUMP TO THE POWER SUPPLY BY MEANS OF A GROUNDED MALE PLUG.
• AT THE STARTING MOMENT THE PUMP SHALL MAKE A KICK, WHICH IS OPPOSITE TO THE

DIRECTION OF THE IMPELLER. ENSURE DIRECTION OF ROTATION IS CORRECT. IN THREE
PHASE UNITS IT IS SUFFICIENT TO INTERCHANGE ANY TWO LEADS OF THE CABLE TO
CHANGE THE DIRECTION OF ROTATION. IN SINGLE PHASE UNITS THE DIRECTION OF
ROTATION IS PRE-SET AT THE FACTORY.

• CHECK THE CURRENT DRAWN BY THE PUMP AT STARTING. IT SHOULD BE LESS THAN THE

FULL LOAD AMPERE RATING OF THE MOTOR INDICATED ON THE NAME PLATE.

PUMP IS DESIGNED TO OPERATE IN FLUIDS WITH pH from 2 – 10.