Metering Pump Assembly:


Assembly Procedures:

1. Install O-Ring (O-S-013), and Check Valve (CV-2000) onto Inlet Body (51050-1).

2. Insert the 9/16” SS Ball (03072) into the Inlet Body (51050-1).

3. Position an O-Ring (O-S-016) onto the notched end of the Cylinder (50940-1).

4. Screw the notched end of the Cylinder (50940-1) into the Inlet Body (51050-1).

Turn by hand until it bottoms on the Inlet Body, “snug tight”.


5. Thread the Lock Nut (50820-1) onto the Cylinder (50940-1) until it bottoms on the

Cylinder shoulder.

6. Install an O-Ring (O-S-016) onto the long threaded end of the Cylinder (50940-

1).

7. Install the Packing Nut (50630-1), and Packing Set (02022-5) onto the Piston

Rod (50360-1).

NOTE:

Care must be taken to not scratch or dent SS Ball.

NOTE:

Take care not to damage the O-ring on the threads.