1. POSITIONING
Consider the following, when determining the position of the thruster unit in order to
ensure the most efficient operation:
Find the point the farthest forward (or aft), while keeping in mind the space available,
given the vessel’s fixtures, space and shape and while respecting the minimum
immersion depth of one full turbine diameter (185 mm).
As far forward
as possible.
90°
Water Line
Always check and make sure that there is enough room to allow for the complete
removal of the VIP unit and enough room for the connection of the electric power
cables. These cables must be able to flex freely without kinking when the VIP goes up
and down.
To install a VIP in the stern, make sure that the turbine flow is clear of all obstacles, or