beautypg.com

Candy FO FDP 299 X User Manual

Page 14

background image

- Operations to be carried out to make a new connection:
• Choose the supply cord in accordance with the recommendations in the table

• The oven must be in situation as shown:

• Pass the supply cord into the clamp.
• Strip the end of each conductor of the supply cord a 10 mm length, by taking in account
the cord for the connection on the terminal block.
• According to the installation and with the help of should have recovered in the first
operation, fix the conductor as shown on the chart.
• Engage the earth wire yellow/green on the earth terminal, tighten the nut and verify the
continuity of the earth.
• Secure the cable clamp.
• Fix the cover.

CABLE

Area

3 G 2,5 mm

3 G 2,5 mm

Connection to
the terminal
block

PH

N

E

PH N

E

To shunt : make
a bridge with a
shunt bar

1 rst Phase
Shunt 1-2
Shunt 2-3
Neutral
Shunt 4-5

Earth

1 rst Phase
Shunt 1

Neutral
Shunt 2

Earth

IMPORTANT: Blue wire = Neutral Yellow/green wire = Earth

For the connection to the terminal block, you must:
• respect the n° 1,2,3,4, and 5,
• tighten the screws,
• do not forget to fix the earth wire (yellow/green) on the earth terminal n° 6