beautypg.com

0 installation – Baxi Potterton Gold HE A Range User Manual

Page 30

background image

30

10.0 Installation

© Baxi Heating UK Ltd 2008

10.4

Fitting The Boiler

1. Lift the boiler using the Lifting Points as shown by the

shaded areas (Fig. 45). The boiler should be lifted by TWO

PEOPLE. Engage the slots at the top rear of the boiler on the

wall plate (Fig. 46) (see Safe Manual Handling page 5).

2. Ease the boiler forwards and remove the sealing caps from

the boiler connections.

NOTE: A small amount of water may drain from the boiler

once the caps are removed.

3. Insert the sealing washers between the valves and pipes on

the wall plate and the boiler connections. THE RUBBER

WASHERS MUST BE USED ON THE GAS CONNECTION.

4. Tighten all the connections.

10.5

Fitting the Pressure Relief Discharge Pipe
(Fig. 47)

1. Remove the discharge pipe from the kit.

2. Determine the routing of the discharge pipe in the vicinity of

the boiler. Make up as much of the pipework as is practical,

including the discharge pipe supplied.

3. The pipework must be at least 15mm diameter and run

continuously downwards to a discharge point outside the

building. See section 6.7 for further details.

4. Utilising one of the sealing washers, connect the discharge

pipe to the adaptor and tighten the nut.

5. Complete the discharge pipework and route it to the

outside discharge point.

IMPORTANT: Make all soldered joints before connecting

to the pressure relief valve.

10.6

Condensate Drain (see section 7.7)

1. Connect the condensate drain to the trap outlet pipe.

Ensure the discharge of condensate complies with any
national or local regulations in force (see British Gas
“Guidance Notes for the Installation of Domestic Gas
Condensing Boilers”.

2. The connection will accept 21.5mm (

3

/

4

in) plastic overflow

pipe which should generally discharge internally into the
household drainage system. If this is not possible, discharge into
an outside drain is acceptable.

Fig. 47

Pressure Relief Valve

Discharge Pipe

Fig. 45

Wall Plate

Suggested Lifting Points

shown as shaded area

Fig. 46