Start-up and check-out – Lochinvar SQUIRE SIT030 User Manual
Page 17

Installation & Operation Manual
17
6
Start-up and Check-out
1. Make sure the system is free of leaks and that air is
purged from the system.
CAUTION
Fix any leaks found before proceeding
further. Leakage from the boiler piping
can result in severe damage to the boiler.
2. Many soldering fluxes contain Zinc Chloride which can
cause severe corrosion damage to stainless steel. After 
completing all domestic water connections, flush the 
indirect water heater thoroughly before leaving the 
installation. This is particularly important if the 
indirect water heater will be unused for an extended 
period of time after installation. Flush the indirect 
water heater by drawing at least three times its volume 
from the tank.
3. Make sure that all electrical connections are made
correctly and that no exposed high voltage wiring is 
present.
4. Make sure that each zone valve or circulator operates
when, and only when, its thermostat calls for heat. Let 
each zone operate long enough to purge any remaining 
air from the system.
5. Set the indirect water heater to the desired temperature.
Because hot water presents a scald hazard, it is best to set 
the thermostat at 120°F or lower and raise it only if 
necessary to provide adequate hot water.
6. Re-enable the burner and allow the boiler to operate.
Make sure that the boiler shuts down when the indirect 
water heater is satisfied.