LRA Linear Residential Actuator Installation Guide
- 26 -
228158 Revision X13 2-3-2009
Gate Operator Installation Checklist
❑
❑
1 . The gate has been checked to make sure it is level and moves freely in both directions .
❑
❑
2 . Potential pinch areas have been guarded so as to be inaccessible
OR have
contact and/or non-contact obstruction sensing devices installed .
❑
❑
3 . The installer has installed one or more contact or non-contact obstruction sensing
devices, in compliance with UL325 requirements for this installation .
❑
❑
4 . If pedestrian traffic is expected, a separate pedestrian gate has been
installed, a minimum of seven feet from the gate . The customer has been
informed that all pedestrian traffic must use the pedestrian gate .
❑
❑
5 . Warning signs have been installed on each side of the gate in highly visible locations .
The customer has been informed that these signs must remain at all times .
❑
❑
6 . There are no controls installed on the gate operator, or within seven feet of the gate .
❑
❑
7 . The installer has properly adjusted the obstruction sensing feature and has tested
the gate to make sure that the gate stops and reverses a short distance with minimal
resistance applied (40 lbs . on a swing gate at the end of the gate, 75 lbs . on a slide gate)
❑
❑
8 . The installer has instructed the customer in the proper use of the gate operator and reviewed
all of the operational functions, obstruction sensing devices, warning beeper and reset, etc .
❑
❑
9 . The installer has instructed the customer in the proper use of the operator’s
manual disconnect feature . The manual disconnect must never be used
while the gate is in motion . The power switch must be turned off before
using the manual disconnect and disengaging the operator .
❑
❑
10 . The installer has reviewed all safety instructions with the customer, and has left
the safety instructions and owner’s information sheets for their reference .
❑
❑
11 . The installer has answered any questions the customer has regarding the
operation of the gate operator and gate operator safety precautions .
❑
❑
12 . The installer has explained to the customer that a regular maintenance
schedule for both the gate and the gate operator is recommended .
By signing this installation checklist, I/we hereby certify that each item listed and checked above has been covered by the
installer and is clearly understood by the customer .
INSTALLER CUSTOMER
Customer’s Signature
Installer’s Signature