g) Replace hand hole gaskets

using the following procedure:
1)
Remove the hand hole assembly

using a 1-1/4" tee handle wrench or

1-1/4" 1/2" drive socket wrench.

Removing hand hole assembly with a

Tee Handle Wrench

2) Remove the old gasket and thor-

oughly clean the surface on the boiler

and the plate.
3) Fit the hand hole assembly as

follows:
a) Place the gasket on the hand hole

plate and ensure that it is seating cor-

rectly.

Do not use any grease, lubri-

cant, or adhesive.
b)
Position the plate in the boiler. Set

the yoke and tighten the securing nut

sufficiently enough to provide a snug

fit. Verify the position of the plate in the

boiler, then make it hand tight and then

snug with wrench about 1/4 turn. Do

not compress excessively.

Illustration shows correct pressure on

gasket.

c) If the gasket leaks while pressure is

being built up, tighten only enough to

stop leakage.

Never tighten more than necessary to

prevent leakage. Excessive tightening

may shorten the life of the gasket.

Illustration shows over compressed

gasket.

d) Refill the boiler with fresh water.

NOTE

After a new Fulton Boiler has been

in operation for several months,

pieces of burned metal will be

found in the space at the bottom of

the boiler. These pieces of metal are

the remains of a light gauge metal

form which was used during manu-

facture for forming the boiler insula-

tion. This is a normal condition and

does not affect the efficiency or the

life of the boiler in any way.

Recommended Annual

Maintenance Schedule

a) Have combustion (CO

2

, O

2

, CO)

and input checked by responsible per-

sonnel.
b) Dirty flues can cause air flow

restrictions resulting in poor combus-

tion and loss of efficiency.

Clean flues as follows:
1)
Remove the burner and flue

cover plate.

2) Wire brush flue passages.

Wire brushing the flue passages.

3) Remove clean out plugs at lowest

part of unit and clean the bottom of

combustion chamber.

Removing clean out plugs.

4) Remove all soot from the top, and

from the clean out plugs at the bottom

with a vacuum cleaner.
5) Replace clean out plugs carefully

so as not to damage insulation and

replace burner and flue cover plates.
c) Flush boiler out if necessary. See

Section 2 for proper procedure for

"Cleaning the Pressure Vessel."
d) Provide annual inspection by a

qualified ASME Boiler inspector.

Maintenance

Remove burner and flue cover plate