Connect the refrigerant lines using the following procedure:
1.

Remove the cap and Schrader core from both the liquid and vapor

service valve service ports at the outdoor unit. Connect low pres-

sure nitrogen to the liquid line service port.

2.

Braze the liquid line to the liquid valve at the outdoor unit. Be sure

to wrap the valve body with a wet rag. Allow the nitrogen to con-

tinue flowing.

3.

Carefully remove the plugs from the evaporator liquid and vapor

connections at the indoor coil.

4.

Braze the liquid line to the evaporator liquid connection. Nitrogen

should be flowing through the evaporator coil.

5.

Slide the grommet away from the vapor connection at the indoor

coil. Braze the vapor line to the evaporator vapor connection. After

the connection has cooled, slide the grommet back into original

position.

6.

Protect the vapor valve with a wet rag and braze the vapor line

connection to the outdoor unit. The nitrogen flow should be exiting

the system from the vapor service port connection. After this con-

nection has cooled, remove the nitrogen source from the liquid fit-

ting service port.

7.

Vent the nitrogen holding charge in the outdoor unit by opening

both service valves slowly and waiting for the pressure to dissi-

pate. Open both the liquid and vapor valves by removing the

plunger cap and with an allen wrench back out counter-clockwise

until valve stem just touches the chamfered retaining wall. If the

service valve is a ball valve, use a crescent wrench to turn valve

stem one-quarter turn counterclockwise to open. Do not overturn

or the valve stem may break or become damaged. See “PRECAU-

TIONS DURING BRAZING SERVICE VALVE”.

8.

Replace the Schrader core in the liquid and vapor valves.

9.

Go to “SECTION V” or “SECTION IV” for orifice or TXV installation

depending on application.

10. Leak test all refrigerant piping connections including the service

port flare caps to be sure they are leak tight. DO NOT OVER-

TIGHTEN (between 40 and 60 inch - lbs. maximum).

11. Evacuate the vapor line, evaporator, and liquid line to 500 microns

or less.

12. Replace cap on service ports. Do not remove the flare caps from

the service ports except when necessary for servicing the system.

13. Release the refrigerant charge into the system since these units

have been shipped from the factory with a nitrogen holding

charge.

14. Replace plunger cap finger tight, then tighten an additional 1/12

turn (1/2 hex flat). Cap must be replaced to prevent leaks.

See "System Charge” section for checking and recording system

charge.
Supplied with the outdoor unit is a Schrader Valve Core and Orifice for

highest sales volume indoor coil. The valve core must be installed in

equalizer fitting of the indoor coil.

SECTION IV: ORIFICE INSTALLATION

Install Schrader Valve Core as follows:

1.

Slide indoor coil out of cabinet far enough to gain access to equal-

izer fitting on the suction line.

2.

After holding charge is completely discharged remove black plas-

tic cap on equalizer fitting.

3.

Install Schrader Valve Core supplied with the outdoor unit into

equalizer fitting using a valve core tool.

4.

Loosen and remove the liquid line fitting from the orifice distributor

assembly. Note that the fitting has right hand threads.

5.

Install proper size orifice supplied with outdoor unit. Refer to sup-

plied Tabular Data Sheet for specific orifice size and indoor coil

match up.

6.

After orifice is installed reinstall the liquid line to the top of the ori-

fice distributor assembly. Hand tighten and turn an additional 1/8

turn to seal. Do not over tighten fittings.

7.

Leak test system.

8.

Replace black plastic cap on equalizer fitting.

9.

Slide indoor coil back into cabinet.

FIGURE 4: Heat Protection

Do not install any coil in a furnace which is to be operated during the
heating season without attaching the refrigerant lines to the coil. The
coil is under 30 to 35 psig inert gas pressure which must be released
to prevent excessive pressure build-up and possible coil damage.

Line set and indoor coil can be pressurized to 250 psig with dry nitro-
gen and leak tested with a bubble type leak detector. Then release
the nitrogen charge.

Do not connect manifold gauges unless trouble is suspected.
Approximately 3/4 ounce of refrigerant will be lost each time a stan-
dard manifold gauge is connected.

Never attempt to repair any brazed connections while the system is
under pressure. Personal injury could result.

Failure to install Schrader Valve Core on orifice applications could
result in total refrigerant loss of the system!

NOTICE