background image

elbows necessary to reach from the appliance

adapter up through the Round Support Box.

Insure that all pipe and elbow connections are

in their fully twist-locked position.

5. Cut hole in the roof centered on the small

hole placed in the roof from Step 2. The hole

should be of sufficient size to meet minimum

requirements for Clearance to Combustibles,

as specified. Continue to assemble lengths of

pipe and elbows necessary to reach from the

ceiling support box up through the roof line.

Galvanized pipe and elbows may be utilized in

the attic, as well as above the roof line. The

galvanized finish is desirable above the roof

line, due to the higher corrosion resistance.

6. Once the pipe sections have been joined, and

run up through the hole in the roof, slip an

elbow strap over the exposed sections, bend

the support straps outwards, and push the

Initial Installation

QUALIFIED INSTALLERS ONLY

V

ERTICAL

I

NSTALLATION

:

1. Check the instructions for required clearances (air spaces) to combustibles when passing through

ceilings, walls, roofs, enclosures, attic rafters, or other nearby combustible surfaces. Do not pack air

spaces with insulation.

2. Set the gas appliance in the desired location. Drop a plumb bob down from the ceiling to the position

of the appliance flue exit, and mark the location where the vent will penetrate the ceiling. Drill a small

hole at this point. Next, drop a plumb bob from the roof to the hole previously drilled in the ceiling,

mark the spot where the vent will penetrate the roof. Determine if ceiling joists, roof rafters, or other

Figure 28: Wall Framing Hole for Vertical Installation.

framing will obstruct the venting system. You may

wish to relocate the appliance, or to offset, to

avoid cutting load bearing members.

3. To install the Round Support Box/Wall Thimble in

a flat ceiling, cut a 10 inch (25.4 cm) square hole

in the ceiling, centered in the hole drilled in Step

2. Frame the hole as shown in Figure 29.

4. Assemble the desired lengths of black pipe and

Vertical

Vent Cap

Roof

Truss

Insulation

Insulation

Guard

Ceiling

Rafter

Support

Collar

Storm

Collar

Roof Flashing

15 feet (4.57m)

Maximum

Vertical

Venting

Interior Wall

Surface

Insulation

Minimum

Clearance to

Combustibles

Exterior

Wall Surface

If installed

on a carpeted

surfacea hearth

is required

Figure 29: Vertical Installation.

22