Maintenance And Service

b) Insert a

5

/

32

” or 4 mm Allen wrench into the

hexagonal key-way of the screw (see Figure 8),

rotate it counter-clockwise until it is free and

extract it.

c) Check that the screw is clean and if necessary

remove dirt.

d) Flip the screw (refer to Figure 9).
e) Using the Allen wrench as shown in Figure 8,

rotate the screw clockwise until a torque of 9 inch

lbs. WARNING! Do not over tighten the screw.

It is recommended that you grip the wrench by

the short side.

f) Verify that if the conversion is from NG to LPG,

the screw must be re-assembled with the red o-

ring visible (refer to Figure 10). If the conversion

is from LPG to NG, the red o-ring of the screw

must be not visible.

Figure 9: Flip valve

screw.

g) Re-attach the black protection

cap that was removed in step a

(Figure 7).

8. Reinstall the burner, brick panels,

log set, embers, and glass door.

Also refer to S

ECONDARY

I

NSTALLATION

- I

NSTALLING

L

OG

S

ET

AND

E

MBERS

. When

re-installing the burner, ensure that

the burner to pilot hood relationship

Figure 10: O-ring on valve screw.

is similar to what is shown in Figure 11. On some units you will need to pay

special attention when installing the burner that the venturi adjustment rod

is properly installed into the venturi adjustment piece welded to the burner

venturi tube

9. Reconnect the main gas line if it was disconnected and open the shut-off valve

at the gas line to the unit.

10. Use a small brush to apply a warm soapy water solution to all gas connections

(use a half dish soap and half warm water). If a gas leak is present, bubbling

will occur. Gas leaks can be repaired by using an approved pipe thread sealant

or approved Teflon tape. NEVER USE AN OPEN FLAME WHEN TESTING FOR

LEAKS.

Figure 8: Removing valve screw.

7. Convert the SIT gas valve:

a) Remove the black protection cap from the HI/LO knob by hand shown in Figure 7.

Figure 11. Ignitor

assembly beside the

burner.

11. Reconnect the electrical power to the unit.
12. Relight the main burner in both the “HI” and “LO” positions to verify proper burner ignition and

operation and proper flame appearance. Also refer to S

ECONDARY

I

NSTALLATION

- L

OG

S

ET

AND

E

MBERS

I

NSTALLATION

for a flame appearance picture.

13. MAKE SURE that the conversion label is installed on or close to the rating label to signify that the