beautypg.com

0 control startup, 1 start the dual unit control, 2 check for operation – Emerson Liebert OpenComms SL-19534 User Manual

Page 5: 3 lead unit schedule & selection, 1 designating the lead intelecool2 unit, 2 schedule, Table 1 switch/jumper settings, Ontrol, Tartup, Start the dual unit control

background image

Control Startup

3

2.0

C

ONTROL

S

TARTUP

2.1

Start the Dual Unit Control

1. Turn the thermostat Off.
2. Turn on power to both InteleCool2 units.
3. Turn on circuit breakers in each InteleCool2. Both green “POWER ON” LED’s and 1 of the green

“LEAD UNIT” LED’s of the Dual Unit Control will be lit if the unit has been properly connected.

4. Turn the thermostat switch to the “Auto” setting.

One or both of the InteleCool2 units should start if the thermostat is in a call for heating or cool-

ing.

2.2

Check for Operation

1. Raise the thermostat setpoint to force a call for heating.
2. Then lower the thermostat setpoint to force a call for cooling.
The InteleCool2 unit’s fans should run when there is a call for either heating or cooling.

2.3

Lead Unit Schedule & Selection

After verifying the connections and startup, the lead unit may be selected and the lead/lag schedule

may be set.

2.3.1 Designating the Lead InteleCool2 Unit

The position of the P4 jumper on the Dual Unit Control board determines which InteleCool2 unit is

the lead unit: the P4 jumper will be on pins 3 and 4, or “NORMAL.”
Designation as the lead unit may be determined externally by checking a unit’s LEAD UNIT LEDs on

the front panel of the DUC

.

The InteleCool2 unit whose LEAD UNIT LED is lit is the lead unit. If the

designation is satisfactory, no changes are necessary.
To change which InteleCool2 unit is the lead unit, place the P4 jumper on pins 1 and 2 or “REVERSE”

on the Dual Unit Control in the InteleCool2 unit chosen to serve as the lead unit.

2.3.2 Schedule

The Dual Unit Control lead/lag schedule may be set with jumpers on the printed circuit board. By

using the P2 and P3 jumpers and Table 1, the jumpers may be placed for the desired number of days

between switchover. The P2 jumper is on the lower right hand corner of the board (see Figure 1). The

P3 jumper is on the lower mid section of the board (see Figure 1).
Table 1

Switch/jumper settings

# Days for Lead/ Lag

Switchover Cycle

P2

P3

8

Pins 8/4DAY

Pins 1 & 2 (SLOW)

4

Pins 4/2DAY

Pins 1 & 2 (SLOW)

2

Pins 4/2DAY

Pins 3 & 4 (FAST)

1

Pins 2/1 DAY

Pins 3 & 4 (FAST)

NOTE
If the lead/lag schedule is changed while the unit is running, the schedule change may not

take effect until the original schedule is completed. Also, the unit will retain the lead/lag order

of the units, even if power is removed, for two to five days, depending on the setting of the P2

and P3 jumpers.