beautypg.com

Installation, Frame capacity, Module placement in the 8900 frame – Grass Valley 8912RDA User Manual

Page 8

background image

8

8912RDA/RDA-D Instruction Manual

Installation

Installation of the 8912RDA module is a process of:

1.

Placing the module in the proper frame slot, and

2.

Cabling signal ports.

The 8912RDA module can be plugged in and removed from an 8900 Series
frame with power on. When power is applied to the module, LED indica-
tors reflect the initialization process (see

Power Up

on page 11

).

Frame Capacity

The 8912RDA module can be installed in all 8900 Series frames but with
varying maximum quantities determined by frame cooling capacity.

Table 1

provides the power capacity, cooling capacity, and maximum

module count for each frame type.

Note

Module capacity figures assume no other modules are in the frame.
X = Not recommended without forced air cooling.

Module Placement in the 8900 Frame

There are ten slot locations in the frame to accommodate either analog or
digital modules. These are the left ten locations. Refer to

Figure 1 on page 9

.

The two slots on the right are allocated for the power supplies. For addi-
tional information concerning the Power Supply module, refer to the 8900
Power Supply manual.

The third slot from the right is allocated for the Frame Monitor or Network
Interface Controller module. These modules provide health monitoring
and control options.

Table 1. Power, Cooling, and Module Capacity of 8900 Frames

Capacity Calculated

8900TX-A

Frame

8900TF-A

Frame

8900TFN-A

Frame

Power (W)

100

100

100

Recommended Module Cooling (W)

30

90

90

8912RDA Modules

10

10

10

8912RDA-D Modules

9

10

10

This manual is related to the following products: