Installation procedures – Thermon FAK-1 User Manual
Page 3
5.
Inspect ends of tubing cover for snug fi t. Apply
additional RTV sealant where needed.
Cut as Required
Tubing Bundle
FAK-1
Top Cover
4.
Fit tubing bundle to bottom half of cover and install
top half. Screw down fi rmly.
INSTALLATION PROCEDURES
2
Tubing
FAK-1
Bottom Cover
RTV
Sealant
3.
Form a gasket by applying RTV sealant to bottom
half of Bulkhead Entry cover and along radius of
upper half.
FAK-1
Bottom Cover
FAK-1
Top Cover
10-32x .75 Pan
Head Screws
10-32 Kept
Nuts
Heat Trace
(if Included)
8
.
Apply RTV bead to back of FAK-1 fl ange prior to
securing to bulkhead.
RTV Sealant
Drilled hole
for bundle
entry
6.
Drill hole matching bundle diameter into bulkhead.
Mark location for U-Bolt entry and drill 1/4”
(7mm) holes through bulkhead.
Drilled holes
for U-Bolt
entry
7
.
Pre-drill FAK-1 with 3/16” (5mm) holes for
securing FAK-1 to bulkhead.
3/16” holes for
securing FAK-1
to bulkhead
(Field Drilled)
1.
Strip back bundle insulation 38mm (1-1/2”) to
76mm (3”) beyond bus connection heat tracing.
If bus connection indentation is less than 305mm
(12”)-381mm (15”) from end of the heat tracing,
proceed stripping the bundle insulation to the next
indentation.
2.
Trim heat tracing to within 305mm - 381mm (12”
- 15”) of the end of the insulation. If self regulating
heat trace proceed to step 3. For Zone-type heat trace
continue with indentifi cation of bus connection on
step 2a.
2a.
Strip back bundle insulation 38mm (1 1/2”) to
76mm(3”) beyond bus connection heat tracing.
If bus connection indentation is less than 305mm
(12”)-381mm (15”) from end of the heat tracing,
proceed stripping the bundle insulation to the next
indentation.
Tubing
Self-Regulating Heat Tracing
Zone Type Heat Tracing
Tubing
Bus Connection
Indentations
(Zone Heater Only)
Heat Tracing
305mm -381mm
(12” - 15”)
Insulation
305mm -381mm
(12” - 15”)
Insulation
Buss
Connection