FAK-1: Split Bulkhead Entry Kit . . .
The following installation procedures are suggested guidelines for
the installation of the FAK-1:
Receiving, Storing and Handling . . .
1. Inspect materials for damage incurred during shipping.
2. Report damages to the carrier for settlement.
3. Identify parts against the packing list to ensure the proper
type and quantity has been received.
4. Store in dry location.
FAK-1: Split Bulkhead Entry Kit
Item
Quantity
Description
1
1
Bulkhead Entry Cover (Top)
2
1
Bulkhead Entry Cover (Bottom)
3
4
Pan-Head S.S. Screws, #10-32 x .75
4
4
Kept S.S. Nuts, #10-32
5
1
Heat Refl ective Tape
6
1
Glass Fiber Tape
7
3
RTV Sealant Tube
8
1
U-Bolt, Washers and Nuts
2
1
3
4
6
5
7
Tools Required . . .
Hacksaw
Screwdriver
FAK-1: Bulkhead Kit Contents . . .
1
Pliers
8
5-1/4”
7-1/2”
1-3/4”
3”
5-1/4”
Dimensions . . .
If Electrically Heat Traced
• To minimize the potential for arcing on electric heat tracing and
fi re caused by product damage or improper installation use
ground-fault protection, the National Electrical Code (NEC) and
Canadian Electrical Code (CEC) require ground-fault protection of
equipment for each branch circuit supplying electric heat tracing.
• Installation must comply with Thermon requirements and be
installed in accordance with applicable national and local codes.
• Component approvals and performance ratings are based on
the use of Thermon specifi ed parts only. User supplied power
connection fi ttings must be listed or certifi ed for intended use.
• De-energize all power sources before opening enclosure.
• Keep ends of bundles, heat tracing and kit components dry before
and during installation.
• Individuals installing these products are responsible for
complying with all applicable safety and health guidelines.
Proper personal protective equipment, or PPE, should be
utilized during installation. Contact Thermon if you have any
additional questions.