9. Locate manifold (Pt. No. B0832 (20) / B0833 (30)) in tab at top of side rails and bolt
as shown. The distance from the side rails to the ends of the manifold should be
equal. [FIG.3(M) (9)]
10. Ensure that both support rails and manifold are in line (centre line of rubber support
pads with centre line of holes in manifold) [FIG.3(M) (10)]. Tighten all bolts.
11. Locate manifold fittings to manifold inlet and outlet. Note that the air vent should be
installed vertically. Check all plumbing and pipe work between collector and hot
water storage tank. Fill the system, switch the circulating pump on and vent the
installation.
12.
Remove the self-tapping screws [FIG.3(M) (11)] and remove the manifold lid.
[FIG.3(M) (12)]
13. Switch on circulating pump
.
14. Make sure there is no leak in piping system.
15. Check system pressure and flow rate.