Internal radio modem configuration, Ntrip setup, Base & rover survey setup – NavCom LAND-PAK Quick Start Rev.B User Manual
Page 7: Land-pak quick-start guide

LAND-PAK Quick-Start Guide
96-310039-3001, Rev. C
7 of 7
74. From the dropdown lists, select:
a. Make: NavCom
b. Model: SF-3040
c. Port: Bluetooth
75. Click Bluetooth Search. The display will update with
SF-3040 and the unit serial number, i.e.: SF304020024.
76. Select the appropriate device and click OK.
77. Click Connect.
Internal Radio Modem
Configuration
This section provides the steps to initially configure the SF-
3040 1W internal radio modem.
The only time you select GPS Reference is
when you are setting up a base station with
the internal 1 W or external UHF radio boost.
78. Click Connect to connect to the SF-3040 receiver.
79. On the Link Configure dialog box (refer to Figure 8),
select Internal UHF Radio as the Link Device. The
GPS Port is Internal, for the 1W radio only.
80. Select a Data Format from the drop-down list.
81. Click Setup.
82. On the Radio Setup dialog (refer to Figure 9), select
the Network ID, type a frequency in the Frequency text
box
(the Base and Rover frequencies and Network ID’s
must match), and select the Transmit Power. On the
Rover, set the Transmit Power to 100mW unless the
base requires the rover position for network corrections
(i.e. a periodic GGA message). In this scenario, set the
rover to match the base power out.
83. Click OK.
Figure 8: Link Configure
84. On the Link Configure dialog box (refer to Figure 8),
click Connect.
Figure 9: Radio Setup
NTRIP Setup
Refer to the following documents (located on the USB thumb
drive) for complete information on configuring NTRIP:
NavCom WM6 Local Internet Guide.pdf
NavCom GPS GSM Profile and Bluetooth Guide.pdf
Base & Rover Survey Setup
Refer to the NavCom FieldGenius.pdf document (located on
the USB thumb drive) for complete information on
configuring the base and rover:
Base reference position
Base reference ID
Output message formats and timing
Rover mode
Authorized base ID’s
Surveying and staking points
Line work
Field to finish work