Installation – Flowserve DK 45 User Manual
Page 10

0
Installation
DK 45
The DK 45 can be installed in horizontal and vertical lines.
In the case of a horizontal installation, make sure that the cover it at the top.
Steam trap with flanges
. Observe correct position of installation.
. Observe direction of flow. The flow arrow is on the trap body.
. Consider space required for opening trap. When the trap is installed a minimum space of at least
70 mm is required for removing the cover
C
.
4. Remove plastic plug. They are only used as transit protection.
5. Clean seating surfaces of both flanges.
6. Install steam trap.
Steam trap with screwed sockets
. Observe correct position of installation.
. Observe direction of flow. The flow arrow is on the trap body.
. Consider space required for opening trap. When the trap is installed a minimum space of at least
70 mm is required for removing the cover
C
.
4. Remove plastic plug. They are only used as transit protection.
5. Clean threads of screwed sockets.
6. Install steam trap.
Danger of severe injuries, death and destruction caused by the explosion of explosive
mixtures.
An electrically insulated installation of the equipment between pipe flanges can generate
static electricity. If the equipment is to be installed in explosive-risk areas, appropriate
measures have to be taken in order to discharge static electricity (earthing)!
Danger