5. The front edge of the sleeve should protrude

1/4” to 1/2” from the finished outside surface

of the wall (Fig. 3).

6. Align the sleeve with the wall so that the

bottom pan is angled 1/2 bubble toward the
outside of the building (Fig. 3).

7. Fasten the sleeve to the wall studs at 3

locations on each side. See

Fig. 2

for

approximate locations. Note: It is

recommended to use fasteners with seal

washers to minimize the possibility of water

leakage into the wall.

8. Connect drain plumbing to the 3/4” pipe

nipple. Note: Drain line may need to be

trapped to prevent sewer gas from entering

the structure. Caution: Damage due to

water leakage will occur if the primary

drain line and secondary drain

passages are obstructed or clogged.

Therefore it is necessary to perform

periodic maintenance to ensure that

drains remain open.

9. Place a bead of silicone sealant or other

high grade non-hardening sealing

compound approved for exterior use to seal

the gap between the wall sleeve and both

the inside and outside wall surfaces (Fig.

3). Sealant should also be applied around

the heads of the fasteners used to secure

the sleeve.

Grille

SPU

Outside

Approximate

Fastener Locations

Wall Sleeve

Disconnect

Figure 2

Return Air

SPU Unit

To Condensate

Drain

6” Min.

1/4” Min.

Sealant

Figure 3

************* Warning *************

Ensure that the bottom of the sleeve

pan is pitched toward the outside to

ensure positive secondary drainage.

********* WARNING *********

Application of the sealant to both

inside and outside surfaces of the

sleeve is critical to prevent

infiltration of outside elements

from entering the structure.

Drain

1/2 Bubble

GRILLE INSTALLATION

1. Remove weather guard.

2. Install 6 threaded studs into the threaded

holes in the grille. Note: Studs, nuts

and washers may be attached to the

grille or may be found in bulk packaging

with the grille shipment.

3. Insert the threaded studs into the slotted

holes in the wall sleeve.

4. Secure grille with a washer and 10-32

nut on each stud.

Electrical

Service Knock-out

********* WARNING *********

The Architectural Grille must be

installed prior to the installation of

the SPU unit into the sleeve.