Robot mounting procedure, Figure 2-2, Mounting hole pattern for robot – Adept i600 Cobra User Manual

Page 20: Performance, Shows the mounting hole patt

background image

Robot Installation

20

Adept Cobra i600/i800 Robot User’s Guide, Rev G

Figure 2-2. Mounting Hole Pattern for Robot

Robot Mounting Procedure

1. Using the dimensions shown in

Figure 2-2

, drill and tap the mounting surface for

four M12 - 1.75 x 36 mm (or 7/16 - 14 UNC x 1.50 in.) machine bolts (bolts not
provided). See

Table 2-2

for bolt and torque specifications.

2. While the robot is still bolted to the transportation pallet, connect the hydraulic

lift to the eyebolt at the top of the inner link (see

Figure 2-1 on page 17

). Take up

any slack, but do not lift the robot at this time.

3. Remove the four bolts securing the robot base to the pallet.

Retain these bolts for possible later relocation of the equipment.

4. Lift the robot and position it directly over the mounting surface.

5. Slowly lower the robot while aligning the base and the tapped mounting holes in

the mounting surface.

WARNING:

Do not attempt to lift the robot at any points

other than the eyebolt provided. Do not attempt to extend
the outer link of the robot until the robot has been secured
in position. Failure to comply could result in the robot
falling and causing either personnel injury or equipment
damage.

+0.015

6

2x R4 0

45

50

10

160

160

200

80

90

+0.015

0

Ø 8

4X Ø 14
THRU

6

234

338

Units in mm