1.

Installation of boiler for new heating system,

Install all of radiation units (panels, radiators,

baseboard, or tubing) and supply and return mains

first. After all heating system piping and components

have been installed, make final connection of system

piping to boiler. It is recommended to mount circulating

pump on supply side piping, such that it pumps away

from expansion tank. Refer to figures on next pages.

2.

Equip hot water boiler installed above radiation

level with low water cut off device. Periodic inspection

is necessary, as is flushing of float type devices, per

low water cut off manufacturer’s specific instructions.

3.

Packaged boiler is set up with 1¼” NPT supply

and return piping from front of boiler. Boiler supply

and return piping can be moved to rear of boiler. Boiler

should not be piped return line to front, supply line

to rear, or vice versa, will cause boiler water to short

circuit heat exchanger. Piping connections may require

additional fittings and parts.

4.

Install drain valve provided with boiler in return tee.

See figure 6.

5.

Install Safety Relief valve in rear section using ¾”

nipple and street elbow provided with boiler. See figure

3.

A. Install safety relief valve with spindle in vertical

position.

B. Do not install shutoff valve between boiler and

safety relief valve.

C. Install discharge piping from safety relief valve.

• Use ¾” or larger pipe.
• Use pipe suitable for temperatures of 375°F

(191°C) or greater.

• Individual boiler discharge piping shall be

independent of other discharge piping.

• Size and arrange discharge piping to avoid

reducing safety relief valve relieving capacity

below minimum relief valve capacity stated on

rating plate.

• Run pipe as short and straight as possible to

location protecting user from scalding and properly

drain piping.

• Install union, if used, close to safety relief valve

outlet.

• Install elbow(s), if used, close to safety relief valve

outlet and downstream of union (if used).

• Terminate pipe with plain end (not threaded).

Low Design Water Temperature Systems (Below 140°

F) And Large Water Content Systems

• Significant condensation may form in this boiler and/

or venting system if boiler is operated with return

temperatures of less than 120°F.

• Condensation is corrosive and can eventually cause

damage to boiler and venting system. Minimum design

return water temperature to prevent this condensation in

boiler and venting is 120°F.

• Boiler used in heating system where design water

temperatures below 140°F are desired (e.g. radiant floor

heating), a 3-way or 4-way mixing valve or suitable

alternative (e.g. Bypass Piping Arrangement shown

in diagram on following page) is required to prevent

low temperature (below return 120°F) return water

from entering boiler. When using mixing valve, follow

manufacturer’s installation instructions.

• Boiler connected to system having large water content

(such as former gravity system), use of Bypass Piping

Arrangement shown in diagram on following page is

suggested.

SYSTEM PIPING

6.

Verify clean cold water supply is available when

connecting to pressure reducing valve. When water

supply is from well or pump, a sand strainer should be

installed at the pump.

Figure 6 - Safety Relief Valve Installation

Follow Instructions

to install discharge

piping from safety

relief valve to drain.