Calibrate system, Set up fixture, Calibrate depth, roll, and pitch – Ditch Witch OnGrade User Manual
Page 30: Ongrade operator’s manual
OnGrade Operator’s Manual
Conduct OnGrade Bore - 29
Calibrate System
CMW
Calibrate System
Set Up Fixture
1.
Unfold calibration fixture away from metal
objects and on reasonably level ground.
2.
Install battery in beacon and place beacon in
beacon housing.
3.
Place beacon and tracker in fixture, as
shown.
•
Left pod of tracker should point toward
beacon end of fixture.
•
Bit end of beacon should point same
direction as tracker display.
4.
Calibrate SmartTool level according to
manufacturer’s instructions.
Calibrate Depth, Roll, and Pitch
Depth
1.
Position beacon housing in appropriate position for type of housing used.
•
End load housing: 12 o’clock position.
•
Side load housing: beacon lid facing tracker.
2.
Select “Beacon Calibration” in “Beacon Settings” menu on tracker and follow prompts. See tracker
manual.
e14om006t.eps
- JT5 (161 pages)
- JT922 (159 pages)
- JT9 (165 pages)
- JT20 (195 pages)
- JT1220 (201 pages)
- JT2020 (203 pages)
- JT25 (203 pages)
- JT30 (245 pages)
- JT60 (218 pages)
- JT100 (243 pages)
- AT Air Hammer (11 pages)
- TK Series Manual (61 pages)
- 8500 (77 pages)
- MR90 (121 pages)
- FT5 (28 pages)
- FM5 (57 pages)
- FM13V (46 pages)
- FM25 (67 pages)
- P80 (71 pages)
- FX20 (100 pages)
- FX25 (119 pages)
- FX30 (149 pages)
- FX50 (141 pages)
- FX60 (157 pages)
- MV800 (111 pages)
- RT Line (115 pages)
- RT30 (97 pages)
- RT45 (203 pages)
- RT55 (177 pages)
- RT100 (161 pages)
- RT115 (252 pages)
- RT120 (223 pages)
- Zahn (105 pages)
- RT80 (203 pages)
- RT115 Q (193 pages)
- RT120 Q (211 pages)
- 100SX (50 pages)
- 410SX (131 pages)
- SK350 (77 pages)
- SK750/SK755 (81 pages)
- SK850 (107 pages)
- SK850 Footings Machine (107 pages)
- 150RT (55 pages)
- 250RT (49 pages)