Commissioning Check List
General
All equipment ordered by the customer is installed.
The unit is level and secure.
The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
All Controller functions for the appliance operate.
All electrical or water connections are to manufacturers specifications and the relevant electrical or
plumbing standards and codes.
Unit - Ducted Evaporative Air Conditioner
The water supply line has been flushed to clear swarf and debris and is free of leaks.
The tank is free of foreign matter and debris and the water isolating tap is turned ON.
Water drainpipe work is completed and sealed.
The water basin fills with water and the float valve closes correctly when the water level is 65-
70mm below the overflow level.
The water pump operates correctly when turned ON at the controller.
The Dialflo water bleed rate is adjusted to suit local water conditions.
The Superclean Dump Valve (option). The tank drains correctly when unit turns off.
The fan deck is correctly located and the fan blade spins freely.
The fan operates through the entire speed range.
The minimum fan speed is correctly set.
Water distribution is even with the filter pads fitted and the air conditioner operating pump and fan.
Areas of high water pressure (Exceeding 500Kpa) a water pressure limiting valve must be fitted in
accordance with AS3500. Consequential damage from high water pressure is not covered by
warranty.