TS60-1010 Platform Scale
4
Forklift Weighing Deck #1 into position between the rails, and gently lower the deck
down onto the wooden blocks. Be sure to accurately line up the front edge of the deck to
the front edge of both side rails.
Loosely bolt the weighing deck to the side rails.
NOTE: Only use short bolts when bolting next to a load cell!
Refer to Fig. 1c.
4) Route the Six Load Cell Cables Out the Left Side Rail Cable Exit Hole
SYNOPSIS:
Load cell cables in the Left Side Rail are fed out the cable exit hole. Load cell cables in
the Right Side Rail are routed across the rear beam of the first weighing deck, and fed
out through the Left Side Rail able exit hole.
a) Route the Cables in Left Side Rail Out the Cable Exit Hole
Unbundle the three load cell cables in the rail. Route the cables under the rail’s top plates
and feed the cables out the exit hole located in the center of the rail’s outside wall.
b) Route the Cables in the Right Side Rail Over to, and Through the Left Side Rail
Cable Exit Hole
Unbundle the three load cell cables in the rail. Route the cables under the rail’s top plates
and out the cable exit hole, then across the rear beam of the first weighing deck, being
sure to feed the cables through the three cable guides on the beam.
Feed all six cables out the cable exit hole on the outside wall of the Left Side Rail.
NOTE: All cables need to have a 20” to 30” length protruding from the exit hole to allow
for making connections into the junction box.
5) Loosely Bolt the Second Weighing Deck Onto the Side Rails
SYNOPSIS:
The second weighing deck is forklifted into position and loosely bolted into place
Forklift the second weighing deck into position, with the top deck slightly overlapping
the rear beam of the first weighing deck in order to mate up the bolt holes.
Loosely bolt the weighing deck onto the side rails.
NOTE: Only use short bolts when bolting next to a load cell!
Refer to Fig. 1c.
6) Securely Bolt Down the Entire Weighing Deck/Side Rails Assembly
Tighten down all bolts connecting the side rails to the weighing decks. Before fully
tightening any bolts, lightly tighten the bolts located at far ends of the rails, and work