3. Make sure to place the side ramp with cable exit notches where the load cell

cables exit.

4. When all ramps are properly aligned, use ½” concrete bit to drill the holes. Install

all anchor bolts and tighten them securely.


Platform to Junction Box Connection


1. Locate an area, approximately 5 feet away from the scale, in which to mount the

indicator/summing junction stand. Secure the stand to the ground with four ½”
anchor bolts.

2. Mount the junction box to the stand with the hardware provided.

3. Feed the six (6) load cell cables through the ribbon conduit provided. Be sure all

six (6) load cell cables are numbered with wire tags.

4. Secure the ribbon conduit to the floor with the ¼” anchors provided.

5. Connect all six load cell cables to their respective terminals on the summing

card. Use the color code chart below for reference.


Load Cell

Color Code

+E Red

-E Black

+S Green

-S White

SH Bare

Junction Box to Indicator Connection

1. Mount the digital indicator to the indicator stand with the hardware provided.

2. Connect the home run cable to the junction box using the same color codes as

above.

3. Make sure to tighten all liquid tight fittings to prevent moisture from entering the

junction box.


Corner Adjustment

The scale ships from the factory with pre-adjusted corners. However, if adjustments are
needed use the potentiometers to adjust each corner as necessary. It is recommended
to use 2,000 lbs of test weight to adjust the corners.