4 Hydraulic Installation

Ensure all pressure has been bled from the system before disconnecting any lines
or fittings. Hydraulic pressure will exist on the main lift circuit unless the main lift
is all the way down.

Component failure due to oil contamination is not covered under the NORAC UC5
system warranty. It is recommended that a qualified technician perform the
hydraulic installation.

1. Use Figure 1 as a reference for installing the hydraulics.

2. Loosen the existing 2-station valve block so that it can be moved and/or twisted for the

installation of the expansion block.

3. Remove all plastic plugs from the NORAC expansion valve block (V01).

4. Coat the four o-rings in hydraulic oil and install them into the expansion block. Ensure the

o-rings are seated properly.

5. Attach the expansion block to the 2 station block using the included spring washers and

bolts.

6. Tighten the bolts to 31 ft-lbs.