9. Connect the UC4 Roll cable C16 to the
three pin shroud on cable C11.
10. Route the DT connectors on C16 to
the Summers valve block.
11. Disconnect the Left tip lift DT
connector from the Summers valve
block and plug it into the connector
marked “ROLL CW” on cable C16.
12. Connect the DT plug labeled “ROLL
CW” on cable C16 into the Left Up
connector on the Summers valve block.
13. Disconnect the Right tip lift DT
connector from the Summers valve
block and plug it into the connector
marked “Roll CCW” on cable C16.
14. Connect the DT plug labeled “ROLL
CCW” on cable C16 into the Right Up
connector on the Summers valve block.
15. Connect the Bypass interface cable
(C13) to the 3 pin tower on cable C11.
16. Route the DT connectors on cable C13
to the Summers valve block.
17. Remove the connector from solenoid H
on the Summers valve and connect the
DT plug on cable C13 to the valve.
18. Connect the plug that was disconnected
from solenoid H to the receptacle on
cable C13.
19. Connect the plug (P01) to the 6 pin
tower on cable C11.
20. Connect the CAN Node cable (C02B)
to the 4-pin AMP plug on C11.
21. Route the CAN Node cable (C02B) to
the roll sensors. Follow existing cables
and/or hydraulic lines.
22. Connect the extension cable C06 to
the CAN Node cable.
Cable C06 should only be
required on 132’ booms.
23. Connect the sensor branch cable (C02)
to the 4-pin AMP plug on C14 .
24. Route the sensor branch cable (C02) to
the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.
25. Cable-tie the installed cables every 12
inches.
IMPORTANT:
Provide enough slack in all cables to
account for the movement of the
main section, parallel lift, and
FOLDING boom movement.