22
7. Route C11 to the rear of the sprayer,
in the vicinity of the valve block.
8. Connect the 6-pin shroud (S6) on C12
to the mating connector (T6A) on C11
(Figure 24).
9. Route the free end of C12 to the Miller
valve block and insert the 2-pin tees
between the matching valve
connections. For each tee, the function
(e.g. “Main Up”) is labeled on the branch
wire.
10. Unplug the connectors on the existing
valves. There are 4 connectors to
unplug (as labeled on the valve bank):
LEFT UP, LEFT DOWN, RIGHT UP and
RIGHT DOWN. Plug in the 2-pin tower
of C12 to the matching existing valve
connections. For each connector, the
function (e.g. “LEFT UP”, etc.) is labeled
on the branch wire.
11. Connect the 6-pin tower on the valve
cable (C03) onto the mating connector
(S6A) on C11 (Figure 24).
12. Route the free end of C03 to the
vicinity of the NORAC valve block.
13. The connectors on the valve cable
(C03) are marked RIGHT UP, LEFT
UP, RIGHT DOWN and LEFT
DOWN. Cables labeled with UP go
on the same side as the hydraulic hoses.
Figure 25: Valve Cable Connections
14. Connect the AMP 4-pin plug – P4 (C11)
to the 4-pin AMP receptacle on the tee
of C05 (Figure 26).
15. Route the sensor roll bias cable (C05)
to the chassis roll sensor. Follow
existing cables and/or hydraulic lines.
16. Connect the CAN Node cable (C02B)
to the 4-pin AMP plug on the tee of
C05 (Figure 26).
17. Route the CAN Node cable (C02B) to
the roll sensors. Follow existing cables
and/or hydraulic lines.
18. Connect the sensor branch cable (C02)
to the 4-pin AMP plug on C02B
(Figure 26).
19. Route the sensor branch cable (C02) to
the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.
20. Cable-tie the installed cables every 12
inches.