R-6. Check installed cables for adequate clearance


One inch clearance is required between the underside of inter-connecting cables and the top of all battery
cases across each tier to accommodate the P3300 hold down strut and KYDEX insulating channel.

If this space is not available due to insufficient cable lengths, new cables of the correct length must be installed.
This situation will require replacing existing cables before going to the next assembly operation.

R-7. Seismic Racks – Install spacer blocks and secure end braces to battery support rail


End Brace

Mounting Hardware – torque to 46 ft lbs
3/8” – 16 Hex bolt

3/8” Flat washer

3/8” Flat washer

3/8” Star washer

Bracing Bracket

3/8” Hex nut

Support Rail






R-8. Install Seismic hold down strut and KYDEX insulator

CAUTION – Avoid shorting battery terminals against hold down strut !!












Repeat this step for each tier.

Place the “U” shaped KYDEX insulating
channel over the “U” shaped Hold down
strut.

Position this assembly so it looks like a
“U”. The KYDEX insulator will now be on
the bottom.

Starting on the lowest tier, at either end of
the rack, slide the hold down strut/insulator
assembly under the inter-cell cables so
that the flat side of the strut assembly rests
CENTERED on top of the battery cases.

Hold down strut assembly

Cable

Spacer block

Battery Support Rail

End Brace

Battery

End brace mounting holes in battery support rail

Support Rail Assembly with Batteries, Spacers, and End Braces

Battery

End Brace
with mounting
hardware

Spacer
Block

Spacer block between end
brace and battery not
required when holes in end
brace match up to holes in
support

rail.