4/5 PrESSurE TEST
Objective: Perform air in water pressure test.
INSPECTION
J-TH34 | PG 5
›
Install male adapter to both hot and cold water inlet.
Figure 4.1
›
Connect female air supply adapter to installed male adapter.
Figure 4.2
›
Install plugs on north and south side outlet ports.
Figure 4.3
›
Turn on air supply.
›
Submerge thermal body into 6 inches of water.
Figure 4.4
›
Rotate check stops in a 360 degree rotation from ON to
OFF, from OFF to ON positions.
Figure 4.5
›
Monitor entire valve for leaks, if no leaks are present valve
is in compliance. Remove from water.
›
Turn off air supply, remove male and female adapters.
Remove north and south plugs.
›
Using compressed air, blow out excess water from thermal
cartridge and stop lock nut, water inlet/outlet, and from
check stops and lock nut locations.
Figure 4.6
4.1
4.3
4.2
4.1
4.2
4.3
4.4
4.5
4.6
4.6
4.6
4.6
Note: If thermal valve body is in non-compliance
status, body must be destroyed by drilling holes
in the base at the center of the check stop
housing.
Figure 5.1
Then place on non compliance shelf.
5.1