5 Putting into operation
36
V-700/710 Operation Manual, Version E
Commissioning option 1 (parallel)
To install the controllers proceed as follows:
• 1. Assemble the corresponding controller holder
as previously illustrated.
• 2. Mount the controller bracket on top of the
pump with the long center screw number (3).
• 3. To mount the metal lever in the designated
angle, turn it until the preinstalled clamb-screw
matches the small hole of the lever. Now, fixate
the lever with the clamb-screw.
• Mount both controllers at the controller bracket.
• Visually align the controllers in parallel at the
metal lever to avoid bending stress of the hoses
and sealings. This will enhance the durability of
the sealing.
• Use the two shorter hoses to connect the valve
unit to the controllers.
• Mount the shortest hose between the valve units
as illustrated in the picture to the left. Check all
sealings for proper function!
Retighten all connections at the pump. Again,
make sure the system is without leakages!
Note
•
It is possible to combine different con-
troller types.
• EasyVac and LabVac are no possible
options for this system.