START-UP CHECKLIST
A. Preliminary Information
COMPRESSOR BEARING UNIT:
MODEL NO.
SERIAL NO.
09BY UNIT:
MODEL NO.
SERIAL NO.
FIELD-INSTALLED ACCESSORIES
B. Pre-Start-Up
CONDENSING UNIT
IS THERE ANY SHIPPING DAMAGE?
(Y/N)
IF SO, WHERE:
WILL THIS DAMAGE PREVENT UNIT START-UP?
(Y/N)
CHECK POWER SUPPLY. DOES IT AGREE WITH UNIT?
(Y/N)
HAS THE GROUND WIRE BEEN CONNECTED?
(Y/N)
HAS THE CIRCUIT PROTECTION BEEN SIZED AND INSTALLED PROPERLY?
(Y/N)
ARE THE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY?
(Y/N)
HAVE DRAINAGE CONNECTIONS BEEN COMPLETED?
(Y/N)
HAVE FAN AND MOTOR PULLEYS BEEN CHECKED FOR PROPER ALIGNMENT?
(Y/N)
DO THE FAN BELTS HAVE PROPER TENSION?
(Y/N)
HAS CORRECT FAN ROTATION BEEN CONFIRMED?
(Y/N)
HAS WATER BEEN PLACED IN DRAIN PAN TO CONFIRM PROPER DRAINAGE?
(Y/N)
ARE PROPER AIR FILTERS IN PLACE?
(Y/N)
CONTROLS
HAVE THERMOSTAT AND INDOOR-FAN CONTROL WIRING CONNECTIONS BEEN
MADE AND CHECKED?
(Y/N)
ARE ALL WIRING TERMINALS (including main power supply) TIGHT?
(Y/N)
HAS CRANKCASE HEATER (IF EQUIPPED) ON UNIT BEEN ENERGIZED
FOR 24 HOURS?
(Y/N)
09BY UNIT
HAS WATER BEEN PLACED IN DRAIN PAN (IF REQUIRED) TO CONFIRM PROPER
DRAINAGE?
(Y/N)
ARE PROPER AIR FILTERS IN PLACE?
(Y/N)
HAVE FAN AND MOTOR PULLEYS BEEN CHECKED FOR PROPER ALIGNMENT?
(Y/N)
DO THE FAN BELTS HAVE PROPER TENSION?
(Y/N)
HAS CORRECT FAN ROTATION BEEN CONFIRMED?
(Y/N)
PIPING
HAVE LEAK CHECKS BEEN MADE AT COMPRESSOR, CONDENSER, EVAPORATOR,
TXVs (Thermostatic Expansion Valves), SOLENOID VALVES, FILTER DRIERS, AND FUSIBLE PLUGS
WITH A LEAK DETECTOR?
(Y/N)
LOCATE, REPAIR, AND REPORT ANY LEAKS
HAVE ALL COMPRESSOR SERVICE VALVES BEEN FULLY OPENED (BACKSEATED)?
(Y/N)
HAVE LIQUID LINE SERVICE VALVES BEEN OPENED?
(Y/N)
IS THE OIL LEVEL IN THE COMPRESSOR CRANKCASE ON THE UNIT IN VIEW IN THE
COMPRESSOR SIGHT GLASS (IF APPROPRIATE)?
(Y/N)
HAS CONDENSER PRESSURE RELIEF BEEN PROVIDED?
(Y/N)
CL-1