Prepare Baffles
Apply Initial Foam Seals
Refer to Figure 5
12. Select all baffles (
,
).
Clean, de-grease and dry the lower flanged edges
of each baffle. This edge is the surface that will be
against the seed box walls and well dividers when in
use.
13. Select both rolls of the new:
890-750C FOAM SEAL 1/2 X 3/4 X 204
14. Apply a single continuous layer of foam seal to the
flanged edges.
Test Fit Baffles
Refer to Figure 3 on page 3
15. Place each baffle in the same locations used for
determining the hole locations at step 7 and step 8.
16. Press down firmly and check the entire flange for
gaps.
17. Mark the first foam layer at any regions showing
gaps.
Apply Additional Foam Seal (As Needed)
Refer to Figure 6
18. Cut and apply additional foam seal
at marked
regions
.
19. Place baffle at its assigned location in the seed box,
and re-check seal seating.
20. Mark baffles (on foam) with numbers of adjacent
rows. Unless all baffles with the same part number
received identical foam application, baffles are now
customized to specific locations in the seed boxes.
Prepare Eyebolt Locations
21. Use a punch to make a detent at the center of any
locations, marked at step 10, where a hole needs to
be drilled.
22. Use the
9
⁄
32
in drill to make holes at all marked loca-
tions.
23. Remove all marked bolts. These bolts, washers and
nuts are not re-used. No precautions need to be
taken to secure parts held together by removed
bolts.
Figure 5
First Layer of Foam Seal
19253
Figure 6
Second Layer of Foam Seal
19254
2