beautypg.com

Assembly, Valves, Hose routing – Great Plains 1500TM Predelivery Manual User Manual

Page 12: Valves hose routing

background image

586-535Q

12/12/2013

8

1200-1500TM

Great Plains Manufacturing, Inc.

Assembly

Valves

Note: Bolts needed in these next steps will be bolted on parts

or located in a bag on center frame. The hoses will be
hooked to valves and cylinders and hoses running to
hitch will be rolled up on center frame. The system will
be charged. Once hitch assembly is installed hoses will
need routed on hitch, see Hose Routing below

Refer to Figure 5
17. Install the counter balance valve

to block on center

frame with 5/16 x 3 1/2 hex bolts

and 5/16 lock wash-

ers.

18. Align holes in double block tee

in position shown,

secure with 5/16 x 4 bolts

, 5/16 lock washers and 5/16

nuts.

19. Install the lock valve

to the top of the bracket on center

frame with 1/4 x 2 Gr. 5 hex bolts

, 1/4 lock washers

and 1/4 nuts.

20. Bolts may be tightened to specs, See “Torque Values

Chart” on page 19.

Hose Routing

Refer to Figure 6

Note: Be sure hoses running from valves

to cylinders are

routed as shown before installing trusses

. The hos-

es need to route in locations shown with arrows, on top
of center frame tubes

to cylinders.

3

4

5

U

D

F

B

L

R

6

Figure 5

Valves

42943

1

2

1

2

3

4

5

6

2

1

Figure 6

Hose Routing

43124

3

2

3

1

2

3

This manual is related to the following products: