Series 5 Toolbar

Operating Instructions

The subsoiler times are manufactured from
40mm thick high tensile steel to reduce
bending in adverse conditions. The tine units
are also shear bolt protected to minimise the
risk of damage to the legs and frame. The
tines feature 2 part pinned-on tips and
replacable wings.

3.2 Work Instructions

Turning:

Before turning, the machine should
be eased out of work while driving.
Likewise, it should eased back into
work once the turn has been
completed.

In work the Series 5 Toolbar can be driven at
speeds between 8-12km/h.

3.3 Checks

The working quality depends on the
adjustments and checks made prior to and
during work, as well as on regular servicing
and maintenance of the component.

Before beginning work it is therefore
important to carry out any necessary servicing
required.

Working Elements

• Are the working elements in good working
order?

3.4 Parking

In order to avoid damage as a result of
moisture, the machine should be parked, if
possible, indoors or under cover.

When manoeuvring the machine,
pay attention to your surroundings.
Ensure that nobody is in the

manoeuvring area (watch for
children!).

• Park the machine on level and solid ground.
• Lower the machine so that it is supported.
• Disconnect hydraulic lines from the tractor.
• Unhitch the machine.

Adjustment / Operation

3.1.3 Tines

Fig. 3.03: Series 5 Toolbar Tines