3 flow diagram, Flow diagram – Metrohm 850 Professional IC Anion MCS User Manual
Page 20

2.3 Flow diagram
■■■■■■■■■■■■■■■■■■■■■■
10
■■■■■■■■
850 Professional IC – Anion – MCS
8 Install sample path connections.
■
Connect the sample degasser (if required) (see Chapter 2.13,
page 39).
■
Connect sample path connections to the injection valve (see
Chapter 2.14.2, page 41).
9 Installing the MSM (see Chapter 2.16, page 46) – with associated
peristaltic pump (see Chapter 2.17, page 49).
10 Connect the MCS (see Chapter 2.18.2, page 54).
11 Connect detector capillaries (see Chapter 2.19, page 57).
12 Mains connection (see Chapter 2.20, page 60).
13 Connect the instrument to the PC (see Chapter 2.20.1, page 60).
14 Initial start-up (see Chapter 3.1, page 65).
15 Install the guard column (if used) (see Chapter 2.21, page 61).
16 Install the separation column (see Chapter 2.22, page 63).
2.3
Flow diagram
Figure 2 Flow diagram with sequential suppression shows the flow paths
with the application of sequential suppression (MSM (2-9) and MCS
(2-10)). The arrangement of the modules in the diagram corresponds to
the front view of the instrument. Liquid containers (eluent bottle, sample
vessel, waste container, auxiliary solutions container) and guard column
(see Chapter 2.21, page 61) are not shown in the diagram. Which pres-
sure screws, connections and couplings are used, is described in the instal-
lation chapters of the individual modules.