9

II. Knock-Down Boiler Assembly

H.

INSTALLING THE JACKET

1. Before jacket can be secured to boiler assembly

tankless heater coil or blank plate must be attached.
Using rubber gasket and bolts provided secure
heater coil or blank plate to boiler extension by
inserting the bolts from the backside of the exten-
sion. Refer to Figure 4.

A

. REMOVAL OF BOILER.

1. Remove, all boiler to skid, hold down fasteners.

Refer to Figure 3.

2. Carefully walk boiler to the edge of skid. Tilt the

boiler back, allowing an edge to rest on the floor,
and remove the skid.

Figure 3: Base on Skid

B

. TEST HEAT EXCHANGER FOR LEAKS before

proceeding with jacket assembly. Heat exchanger,
canopy, and base are preassembled.

1. Install pressure gauge supplied, a hose to the city

water and a valve in the supply tapping. Plug
remainder of tappings.

2. Fill boiler with water and apply a pressure of at

least 10 psig but no more than 30 psig.